Thursday 18 April 2013

PCI Completed. Handover date - next Wednesday

We had our PCI today. Took close to 3 hours but nothing major spotted. Mainly touch-ups for paint, and 1 minor issue with a missing data point. Our driveway will be poured on either Saturday or Monday and our letterbox will be installed after that.

We've been given a handover date of Wednesday the 24th of April.

























Sunday 7 April 2013

Tiling completed. Final coat of paint started.

Went for a visit this morning to see that the painters were there doing the final coat. Tiling has also been completed. That just leaves our carpets, rendering of the front pier and driveway to go.